Things have been moving very quickly, thanks to our amazing network of subcontractors. Here is a partial list if you like metrics:

- 728 lineal feet of concrete footings were poured with rebar uprights every 4'

- Just under 4,000 blocks were laid for stem walls

- Blocks were filled with 30 cubic yards of concrete, with rebar inserted to tie into slab, and 1/2" galvanized anchor bolts every 4'

- 58 truckloads of sand clay were placed and compacted inside the homes stem walls 

- 41 truckloads of fill were placed and rough graded around the exterior

- Temporary power was pulled underground and passed inspection today (12/8/23)

- 3rd party soil compaction testing to occur today (12/8/23)

- Underslab plumbing began today (12/8/23)