Things have been moving very quickly, thanks to our amazing network of subcontractors. Here is a partial list if you like metrics:
- 728 lineal feet of concrete footings were poured with rebar uprights every 4'
- Just under 4,000 blocks were laid for stem walls
- Blocks were filled with 30 cubic yards of concrete, with rebar inserted to tie into slab, and 1/2" galvanized anchor bolts every 4'
- 58 truckloads of sand clay were placed and compacted inside the homes stem walls
- 41 truckloads of fill were placed and rough graded around the exterior
- Temporary power was pulled underground and passed inspection today (12/8/23)
- 3rd party soil compaction testing to occur today (12/8/23)
- Underslab plumbing began today (12/8/23)