Things have been moving very quickly, thanks to our amazing network of subcontractors. Here is a partial list if you like metrics:

- 728 lineal feet of concrete footings were poured with rebar uprights every 4'

- Just under 4,000 blocks were laid for stem walls

- Blocks were filled with 30 cubic yards of concrete, with rebar inserted to tie into slab, and 1/2" galvanized anchor bolts every 4'

- 58 truckloads of sand clay were placed and compacted inside the homes stem walls 

- 41 truckloads of fill were placed and rough graded around the exterior

- Temporary power was pulled underground and passed inspection today (12/8/23)

- 3rd party soil compaction testing to occur today (12/8/23)

- Underslab plumbing began today (12/8/23)


09Nov

For many years, the family we are building for has had a weekender home on this amazing lot. They made many great memories here, and so it was bittersweet when we demolished this leagacy home to make way for a their new permanent residence.

We have completed demolition on our latest Lake Murray custom home project. A big thank you to our friends at Mett's Construction for coming through (as they always do)! Stay tuned for the start of footings...