Well, 2023 is almost over. It has been a busy year, and an especially busy fall/winter thus far. We have been pushing hard on our latest build, in order to meet our goal of starting framing right after the new year. To accomplish that, we had to pour the slab before the holidays. 

It really took a team effort between many of the finest subcontractors that the Midlands has to offer... but we did it. In fact, yesterday was 'pour day'. We placed 84 yards of concrete, starting at 6 AM, and working the finish until approximately 11PM (due to the very cool weather). What a dedicated crew! We are extremely pleased with the quality of the job and the slow drying conditions... the Client will have a very good base on which we can build their dream home.

We are going to take the next week and spend some well earned time with family and friends. Happy Holidays to you all, and we'll see you in the New Year!

08Dec

Progress Report of 8 December 2023

Things have been moving very quickly, thanks to our amazing network of subcontractors. Here is a partial list if you like metrics:

- 728 lineal feet of concrete footings were poured with rebar uprights every 4'

- Just under 4,000 blocks were laid for stem walls

- Blocks were filled with 30 cubic yards of concrete, with rebar inserted to tie into slab, and 1/2" galvanized anchor bolts every 4'

- 58 truckloads of sand clay were placed and compacted inside the homes stem walls 

- 41 truckloads of fill were placed and rough graded around the exterior

- Temporary power was pulled underground and passed inspection today (12/8/23)

- 3rd party soil compaction testing to occur today (12/8/23)

- Underslab plumbing began today (12/8/23)